How federal agencies can move existing applications into a FedRAMP-certified cloud environment on a fixed-price, wave-by-wave plan, with control evidence mapped to NIST SP 800-53 and an illustrative five-year cost model.
Most federal IT dollars never reach modernization. GAO reports that the government spends more than $100 billion a year on IT and cyber investments and that agencies typically put about 80 percent of it toward operating and maintaining existing systems (GAO-25-107795, July 2025). The same report found that only 3 of the 11 most critical legacy systems it reviewed had fully documented modernization plans. The money, the mandates and the risk all point the same way: out of aging data centers and into authorized cloud environments. What most agencies lack is the engineering capacity to make the move without disrupting the mission.
This paper is written for the people who own that problem: agency and component CIOs, program and mission-system owners, CISOs and ISSMs, cloud program offices, and the contracting officers who buy the work. It describes how Avalon Technology Services delivers Cloud Migration & Development: the planned move of an agency's existing applications, databases and workloads into a FedRAMP-certified cloud environment, plus the code remediation needed to make those systems run properly once they arrive.
The engagement is built around four commitments:
Section 7 presents an illustrative five-year cost model for a representative 30-application portfolio. Under its stated assumptions, the migration costs $2.23M less than the status quo over five years (net present value $2.14M at the OMB Circular A-94 real discount rate) and pays back in Year 2. The model also shows the case that does not work: when no hardware refresh or licensing event falls inside the five-year window, the savings roughly break even. That is why the fixed-price assessment compares both cost paths for the agency's actual portfolio before a single migration dollar is obligated.
Legacy infrastructure rarely fails all at once. It gets more expensive, harder to staff and harder to secure every year, until a single event forces a decision. Four kinds of risk converge on it.
| Risk | How it shows up at an agency |
|---|---|
| Cost | Operations and maintenance consume most of the IT budget. Hardware refresh cycles and post-acquisition licensing changes (VMware under Broadcom is the current example) produce sudden, unbudgeted six- and seven-figure bills. |
| Mission | Fragile systems with single points of failure, limited disaster recovery and hardware past end of support put beneficiary-facing and warfighter-facing services at risk of outage. |
| Compliance | Zero trust architecture, the event logging OMB M-26-14 asks agencies to plan for, and continuous monitoring are difficult or impossible on legacy platforms. Audit and IG findings accumulate against systems that cannot be patched or instrumented. |
| Staffing | The people who understand these systems are retiring or have left, and recent federal workforce reductions make people-intensive legacy operations harder to sustain. |
In practice, migration starts when one of these lands on a program manager's or CIO's desk:
GSA's OneGov program has negotiated government-wide terms with the major cloud providers. The AWS agreement, announced August 7, 2025, provides up to $1 billion in incentive credits across federal civilian agencies, including modernization and training credits, through December 31, 2028. Credits like these lower the agency's consumption bill without touching the migration services price, which is why Avalon checks credit eligibility during every assessment. The remaining constraint for most agencies is engineering capacity, not cloud pricing.
Executive Order 14028 (as amended by EO 14306 in June 2025), the federal zero trust strategy in OMB M-22-09, and the risk-based logging model in OMB M-26-14, which replaced M-21-31 in May 2026, all assume modern, instrumented infrastructure. Identity federation, micro-segmentation and centralized logging are native to a well-built cloud landing zone and very hard to retrofit onto a legacy data center. For many agencies, migration is the practical first step toward meeting these requirements.
Cloud Migration & Development has two halves. The infrastructure half moves workloads into the target environment. The development half fixes what breaks when they get there: hard-coded addresses and file paths, unsupported dependencies, integrations, authentication and build pipelines. Moves that skip the second half are how agencies end up with systems that technically run in the cloud and cost more than they did on premises.
| Strategy | What it means | Typical use |
|---|---|---|
| Rehost | Move the workload as-is to cloud infrastructure | Stable applications with no near-term change planned |
| Replatform | Move with targeted changes, such as a managed database | Applications that benefit from managed services without a rewrite |
| Refactor | Change the code or architecture to run cloud-native | A small number of high-value applications; larger portfolios move to Application Modernization |
| Repurchase | Replace with a SaaS product | Commodity functions such as ticketing, HR or collaboration |
| Retire | Turn it off | Duplicate or unused applications found in discovery |
| Retain | Leave it where it is for now | Systems with a pending decision, a hard dependency or a separate modernization path |
| Relocate | Move a virtualized environment without changing it | Bulk moves of a virtualization estate as a bridge step |
| Deliverable | Format |
|---|---|
| Application portfolio assessment and disposition report | Written report plus a spreadsheet inventory the agency keeps |
| Migration strategy and wave plan | Written plan with schedule, dependency map and risk register |
| Landing zone and environment configuration | Infrastructure-as-code repository (Terraform or cloud-native templates) turned over to the agency |
| Migrated, validated workloads | Operating systems in the target environment, accepted against written criteria |
| Cutover runbooks and rollback plans | Step-by-step runbooks, one per wave |
| Security control implementation evidence | Control-mapped package formatted for the agency's SSP and assessment |
| As-built architecture documentation | Diagrams and narrative, delivered at closeout |
| Knowledge transfer | Working sessions with agency staff, recorded where permitted, plus written operating procedures |
Clear boundaries protect the agency's budget and schedule as much as Avalon's. These items are deliberately outside the migration scope:
| Not included | Where it belongs instead |
|---|---|
| Issuing or guaranteeing an ATO, or performing the independent control assessment | The agency's assessors and Authorizing Official; Avalon's ATO Process Facilitation service can support the process |
| Rewriting a major application portfolio | Application Modernization, scoped and priced separately |
| Building new applications | Cloud Native Development |
| 24/7 operations and monitoring after hypercare | Enterprise Monitoring or a separate O&M task |
| Post-migration cost optimization and spend governance | FinOps, the natural follow-on |
| Designing the target architecture from scratch | Cloud Architecture & Engineering; an existing architecture is validated, not rebuilt |
| The cloud provider's own FedRAMP status | The provider and the FedRAMP program; Avalon lands workloads only in already-certified environments |
The phase plan below assumes a small-to-mid unclassified portfolio of roughly 10 to 25 applications. A pilot wave proves the pattern and calibrates the estimates before the production waves commit.
| Phase | Activities | Duration |
|---|---|---|
| 0. Kickoff and access | Accounts, network access, security paperwork, stakeholder map, data call issued | 1–2 weeks |
| 1. Discovery and assessment | Inventory, dependency mapping, disposition workshops, sensitivity classification | 3–6 weeks |
| 2. Planning and landing zone | Wave plan, target architecture validation or build, infrastructure-as-code baseline, runbook templates | 4–8 weeks (overlaps Phase 1) |
| 3. Pilot wave | One to three low-risk applications migrated end to end | 4–6 weeks |
| 4. Production waves | Remaining waves in sequence; remediation development runs in parallel | 8–24+ weeks, depending on portfolio |
| 5. Cutover and hypercare | Per-wave cutover and validation, with 2–4 weeks of hypercare per wave | Runs alongside Phase 4 |
| 6. Closeout and transition | As-builts, security evidence package, knowledge transfer, decommissioning support | 2–3 weeks |
Total duration scales with application count, data volume, the number of interfaces per application and, above all, the agency's own change-control and testing pace. As a planning guide, 5 to 15 applications take about four to six months, and 15 to 50 applications take six to twelve months. Portfolios of more than 50 applications, or any classified or IL5+ scope, run 12 to 24 months or more and should be structured with option years.
| Role | Involvement |
|---|---|
| Cloud technical lead and architect (founder-level) | Full-time through the pilot wave, then 50–75% |
| Migration engineers (2–3, depending on wave size) | Full-time during the pilot, production waves and cutover |
| Remediation developers (1–2) | As dispositions require, during production waves and cutover |
| Compliance specialist (ISSO support) | 25–50%, concentrated in discovery, planning and evidence packaging |
| Project manager | 25–50% throughout |
Agency-side dependencies are the most common reason migrations slip. Each item below goes into the statement of work as a government-furnished item with a named owner and a date:
A migration changes the system boundary, so the agency will reassess and reauthorize the system in its new environment. Avalon's job is to make that reassessment faster by producing control implementation evidence as a normal output of the engineering work, not as a paperwork exercise after the fact.
Stated precisely: Avalon migrates the system into a FedRAMP-certified environment at the required baseline and delivers control implementation evidence mapped to NIST SP 800-53, reducing the documentation lift for the agency's assessment and authorization.
| Framework | How the migration maps to it |
|---|---|
| FISMA and NIST RMF (SP 800-37) | Migration work sits in RMF Step 3 (Implement) and produces the evidence Step 4 (Assess) uses. Assessment and authorization remain the agency's steps. |
| NIST SP 800-53 Rev. 5 | Landing zone and workload configuration implement customer-responsibility controls, most heavily in the AC, AU, SC, CM, CP and IA families. Evidence identifies which controls are inherited from the cloud provider and which the agency implements, using the provider's customer responsibility matrix. |
| FedRAMP | Workloads land only in FedRAMP-certified offerings at the required baseline. Under FedRAMP's 2026 Consolidated Rules, the program is moving from "authorized" to "certified" terminology, with lettered classes replacing Low, Moderate and High (Moderate becomes Class C); the underlying control baselines do not change. |
| DoD Cloud Computing SRG | For DoD work the target environment must hold the right DISA provisional authorization for the impact level. Avalon's current delivery scope covers IL2 and IL4. |
| Zero trust (EO 14028, OMB M-22-09, DoD ZT Strategy) | Identity federation, segmentation and centralized logging are built into the landing zone, giving the agency a practical starting point for its zero trust milestones. |
| OMB M-26-14 | A centralized log architecture in the landing zone is how agencies reach the EL1 to EL3 event logging tiers. |
| NIST SP 800-171 | Avalon safeguards any CUI it receives during the engagement under SP 800-171. This service does not deliver CMMC certification to anyone. |
Avalon performs migration engineering, security hardening and documentation. Avalon does not certify compliance, does not perform the independent assessment, and does not issue or guarantee an ATO. FedRAMP certification belongs to the cloud provider under the FedRAMP program, and the authorization decision rests with the agency's Authorizing Official. After migration, three things still require separate work: the independent control assessment, the Authorizing Official's risk acceptance and ATO decision, and ongoing continuous monitoring.
Federal migrations are usually priced three ways at once: a fixed-price assessment, fixed-price execution per wave, and time-and-materials for remediation development where code condition cannot be known in advance. Avalon uses that structure and treats fixed price per wave as the default, because it pays for finished waves, not billed hours.
| Scope tier | Typical portfolio | Typical total price |
|---|---|---|
| Assessment and migration plan (entry engagement) | Up to about 50 applications inventoried and dispositioned | $50K–$150K, firm fixed price |
| Small migration | 5–15 applications, unclassified | $250K–$900K |
| Mid migration | 15–50 applications, mixed complexity | $900K–$3M |
| Large or multi-year | 50+ applications, or IL5+ or classified scope | $3M–$10M+, with option years |
These are market-norm planning ranges. Every figure is validated against the specific portfolio during the assessment before it appears in a proposal.
Per-application yardsticks help agencies sanity-check a quote: a simple rehost typically runs $15K to $75K, a replatform $50K to $150K, and a targeted refactor $150K to $500K or more. A portfolio full of refactors is an Application Modernization engagement and is priced separately.
Migration of existing systems is funded mostly with one-year O&M money. That creates two natural buying windows: the second and third quarters, when spend plans firm up, and the fourth-quarter obligation window before September 30. A fixed-price assessment is a clean fit for either. It is firm fixed price, quick to award and severable from the larger effort, and it produces the disposition list that defines and de-risks every wave that follows.
This is an illustration, not a quote and not a result. It models a representative, unclassified portfolio of 30 applications so that agencies can see how the cost components interact. Every input is listed in Appendix C, and every figure is recalculated from those inputs. The assessment replaces these assumptions with the agency's own numbers.
Of the 30 applications, the disposition workshops in this example retire 4, move 3 to SaaS, rehost 12, replatform 8, refactor 2 and retain 1 on premises. Avalon's services for this scope total $2.04M, inside the mid-migration band above:
| Avalon service component | Price |
|---|---|
| FFP assessment and migration plan | $85K |
| Landing zone validation, pilot wave setup and evidence packaging | $210K |
| Rehost waves (12 apps x $40K) | $480K |
| Replatform waves (8 apps x $95K) | $760K |
| Targeted refactor, T&M ceiling (2 apps x $250K) | $500K |
| Total Avalon services | $2,035K |
The status quo keeps the legacy environment running at $3.40M a year and pays a $2.40M hardware refresh in Year 1. The migration path pays for Avalon's services, the agency's own program costs and a year of dual running, then runs at $2.79M a year from Year 2. Figures are in constant FY2026 dollars, in millions.
| Year | Status quo | Avalon services | Agency program costs | Run costs (legacy + cloud) | Migration path total | Cumulative difference |
|---|---|---|---|---|---|---|
| Year 1 | 5.80 | 2.04 | 0.80 | 3.17 | 6.01 | -0.21 |
| Year 2 | 3.40 | 0.00 | 0.00 | 2.79 | 2.79 | 0.40 |
| Year 3 | 3.40 | 0.00 | 0.00 | 2.79 | 2.79 | 1.01 |
| Year 4 | 3.40 | 0.00 | 0.00 | 2.79 | 2.79 | 1.62 |
| Year 5 | 3.40 | 0.00 | 0.00 | 2.79 | 2.79 | 2.23 |
| Total | 19.40 | 2.04 | 0.80 | 14.34 | 17.17 | 2.23 |
What the model shows
A model is only useful if it shows where it breaks. Each row changes one assumption and leaves the rest at the base case.
| Scenario | 5-year difference | NPV (1.3%) | Payback |
|---|---|---|---|
| Base case | $2.23M | $2.14M | Year 2 |
| Cloud consumption 30% higher | $0.74M | $0.70M | Year 3 |
| Only 2 sustainment FTE released | $0.91M | $0.87M | Year 2 |
| Avalon services 25% higher | $1.72M | $1.63M | Year 3 |
| No hardware refresh due in the window | -$0.02M | -$0.10M | Beyond Year 5 |
| CSP modernization credits of $250K applied | $2.48M | $2.39M | Year 1 |
Two findings matter most. First, the case depends heavily on a trigger event: if no hardware refresh or licensing repricing falls inside the window, the migration roughly breaks even over five years and the argument rests on risk, compliance and staffing rather than cost. Second, the savings are sensitive to how many sustainment staff the agency actually redeploys and to post-migration cloud governance, which is why cost governance (FinOps) is the recommended follow-on.
| ID | Risk | Likelihood | Impact | Mitigation built into the plan |
|---|---|---|---|---|
| R-1 | Agency SMEs, access or test staff are unavailable when a wave needs them | High | High | Government-furnished items with owners and dates in the SOW; readiness checklist at every wave gate; schedule relief tied to missed dates |
| R-2 | Rehosts quietly turn into refactors mid-wave | Medium | High | Signed disposition list is contractual scope; changes go through a written change process; extra refactors are quoted separately |
| R-3 | Data migration takes longer than the compute move | Medium | High | Database migration estimated as its own workstream; replication and reconciliation testing rehearsed in the pilot wave |
| R-4 | Cutover disrupts a mission-critical period | Low | High | Wave plan built around the mission calendar; rehearsed cutover with a tested rollback plan |
| R-5 | Cloud consumption exceeds the estimate | Medium | Medium | Rightsizing during replatform; tagging and budgets in the landing zone; FinOps review at closeout |
| R-6 | Reauthorization of the new boundary stalls | Medium | Medium | Early engagement with the Authorizing Official; control evidence delivered wave by wave, not at the end |
| R-7 | No one owns operations after hypercare | Medium | Medium | Operations plan agreed in the first conversation; transition-to-O&M plan attached to closeout |
Cloud migration services are bought through a handful of pathways. The table below states plainly which ones Avalon can use directly and which it would reach through a prime.
| Vehicle | Relevance to cloud migration | Avalon's access |
|---|---|---|
| GSA Multiple Award Schedule (SIN 518210C Cloud Professional Services; 54151S IT Professional Services) | The main pathway for civilian migration task orders and BPA calls | Priority vehicle Avalon is pursuing |
| NASA SEWP VI | Contract period starts November 1, 2026; Categories B and C cover IT services, and all categories support small business set-asides | Near term, as a subcontractor to Category B or C holders |
| OASIS+ small business pools | Services contract with continuous on-ramping; migration fits its technical domains | On-ramp candidate as Avalon's project portfolio grows |
| GSA Alliant 3 | Large-business IT GWAC; first awards made February 2026 | Subcontractor to awardees |
| DoD enterprise cloud contracts (JWCC) | Cloud consumption flows through the cloud provider primes | Migration services alongside consumption, on a services vehicle or as a subcontract |
| Small business set-asides and agency BPAs | Competitive set-asides under NAICS 541512 and 518210, and calls against agency cloud support BPAs | Direct |
Contract type. Firm fixed price is the default for the assessment and each wave, because both are definable and agencies prefer fixed price for this kind of work. Time-and-materials or labor-hour fits the remediation development workstream when code condition is unknown at award. A "start small, expand competitively" strategy (a fixed-price assessment first, then waves) keeps each award small enough to move quickly.
Small business credit. Awarding directly to a small business gives the agency credit toward its small business goals, and a fixed-price assessment or first wave fits comfortably within simplified acquisition approaches. Contracting officers should confirm current thresholds, which are adjusted periodically.
Most stalled migrations trace to a short list of causes. The plan addresses each one in the statement of work, not in a slide.
| Failure point | What happens | How the plan prevents it |
|---|---|---|
| Scope creep | "While you're in there" turns a rehost into a refactor and blows the budget | The signed disposition list is scope; every SOW states that changes to dispositions are a change in scope |
| Compliance oversell | A vendor implies the system will be "authorized" at cutover, and the Authorizing Official disagrees | Avalon uses the precise compliance statement in Section 5 and delivers evidence, not promises |
| Agency-side dependencies | SME time, account provisioning and test staffing slip, and the schedule slips with them | Each dependency is a dated government-furnished item with a named owner |
| Data migration as a footnote | Schema conversion and reconciliation take longer than the server move | Data migration is estimated and staffed as its own workstream |
| No one runs it afterward | Hypercare ends and the agency has no operations plan | Operations ownership is settled at the start; closeout includes a transition-to-O&M plan |
A completed migration is a starting point. The work that follows is predictable, and planning for it early keeps the new environment from drifting back into the problems the migration solved.
| Next step | Why it follows migration |
|---|---|
| FinOps and cost governance | Consumption begins at cutover; tagging, budgets and rightsizing keep the savings in the model from eroding |
| Enterprise Monitoring | Someone has to run and watch the environment after hypercare |
| DevSecOps and CI/CD | Refactored and replatformed applications now deploy as code |
| Zero Trust Architecture | The landing zone's identity, segmentation and logging are the base layers for zero trust milestones |
| SSP development and ATO facilitation | The evidence package from migration feeds the agency's system security plan and assessment directly |
The calendar also matters. SEWP VI opens for orders on November 1, 2026. The AWS OneGov credits run through December 31, 2028. DoD's target-level zero trust deadline falls at the end of FY2027. Under FedRAMP's 2026 Consolidated Rules, solicitation and authorization language is moving to the new certification terminology. Each of these has a migration dependency built into it.
Agencies do not need another modernization vision. They need their systems moved, on a schedule they can plan around, at a price they can defend, with the security evidence their assessors will ask for. Avalon delivers cloud migration as fixed-price waves led by senior engineers, with clear boundaries on what the work includes and an honest statement of how much Avalon can take on at once.
The first step is a fixed-price assessment and migration plan. It inventories and dispositions the portfolio, builds both cost paths from the agency's real numbers, names the government-furnished items that will decide the schedule, and prices each wave before any migration dollar is committed. To discuss an assessment, contact Avalon Technology Services at contact@AvalonTechServices.com.
ATO: Authority to Operate
The Authorizing Official's formal decision to accept the risk of operating a system, issued under the NIST Risk Management Framework.
CSP: Cloud Service Provider
A company that provides cloud infrastructure, platform or software services, such as AWS, Microsoft, Google or Oracle.
CUI: Controlled Unclassified Information
Government information that requires safeguarding under law, regulation or policy but is not classified.
FedRAMP
The federal program that standardizes security assessment of cloud products. Under its 2026 Consolidated Rules it certifies cloud offerings in lettered classes; agencies still authorize their own use.
FFP: Firm Fixed Price
A contract type where the price does not change with the contractor's actual cost.
IaC: Infrastructure-as-Code
Managing infrastructure through version-controlled configuration files rather than manual setup.
IL: Impact Level
DoD's categories for cloud data sensitivity under the Cloud Computing SRG: IL2 (public and low-sensitivity), IL4 (CUI), IL5 (higher-sensitivity CUI and national security systems) and IL6 (classified up to Secret).
Landing zone
The pre-configured cloud foundation (accounts, identity, network, logging and guardrails) that migrated workloads land in.
O&M: Operations and Maintenance
The recurring cost of running existing systems, and the one-year appropriation that usually funds it.
RMF: Risk Management Framework
The NIST SP 800-37 process agencies use to categorize, secure, assess, authorize and monitor systems.
SOW: Statement of Work
The contract document that defines scope, deliverables and government-furnished items.
Wave
A group of applications migrated together, planned by dependency, risk and mission calendar.
The tables below show how migration activities support common control sets. They describe where the work produces evidence; they are not a statement that any system is compliant.
I. NIST SP 800-53 Rev. 5 (selected customer-responsibility controls)
| Control | Name | How the migration supports it |
|---|---|---|
| AC-2 | Account Management | Cloud accounts and roles federated to the agency identity provider and defined in code |
| AU-2 / AU-6 | Event Logging; Audit Record Review | Centralized log architecture in the landing zone aligned to the agency's OMB M-26-14 logging plan |
| CM-2 / CM-6 | Baseline Configuration; Configuration Settings | Configuration baselines captured as infrastructure-as-code and delivered to the agency |
| CP-9 / CP-10 | System Backup; Recovery and Reconstitution | Backup and recovery configured and tested per wave, with rollback plans in each runbook |
| IA-2 | Identification and Authentication | Application authentication moved to the agency's identity provider with MFA |
| SC-7 | Boundary Protection | Network segmentation and controlled ingress and egress in the landing zone |
| SC-28 | Protection of Information at Rest | Encryption baselines applied to storage and databases |
II. ISO/IEC 27001:2022 (selected Annex A controls)
| Annex A control | Name | How the migration supports it |
|---|---|---|
| A.5.9 | Inventory of information and other associated assets | Portfolio inventory and dependency map delivered in the assessment |
| A.5.15 | Access control | Role-based access defined in code and federated to the agency identity provider |
| A.5.23 | Information security for use of cloud services | Shared-responsibility mapping using the provider's customer responsibility matrix |
| A.8.9 | Configuration management | Version-controlled configuration baselines |
| A.8.15 | Logging | Centralized logging built into the landing zone |
| A.8.32 | Change management | Wave gates and the disposition change process |
III. ISO 9001:2015 (quality management)
| Clause | Requirement | How the migration supports it |
|---|---|---|
| 8.1 | Operational planning and control | Wave plan, runbooks and written acceptance criteria |
| 8.5.1 | Control of production and service provision | Rehearsed cutovers with defined validation steps |
| 9.1 | Monitoring, measurement, analysis and evaluation | Per-wave acceptance results and hypercare issue tracking |
| 10.2 | Nonconformity and corrective action | Pilot-wave lessons applied to production wave estimates and runbooks |
All values are Avalon planning assumptions for a representative portfolio, in constant FY2026 dollars. None is drawn from a specific agency or a completed engagement.
| Category | Assumption | Basis |
|---|---|---|
| Portfolio | 30 applications: retire 4, repurchase 3, rehost 12, replatform 8, refactor 2, retain 1 | Representative mid-size unclassified portfolio |
| Legacy run cost | Sustainment labor (10 FTE): $1,650K per year | Avalon planning assumption |
| Legacy run cost | Data center hosting, power and space: $600K per year | Avalon planning assumption |
| Legacy run cost | Hardware maintenance contracts: $250K per year | Avalon planning assumption |
| Legacy run cost | Virtualization, OS and database licensing: $900K per year | Avalon planning assumption |
| Legacy refresh | Hardware refresh of $2.40M due in Year 1 (status quo only) | The trigger event in this example |
| Target run cost | Sustainment labor (6 FTE): $990K per year from Year 2 | Avalon planning assumption |
| Target run cost | Cloud consumption, 22 migrated apps (rightsized): $1,100K per year from Year 2 | Avalon planning assumption |
| Target run cost | SaaS subscriptions, 3 repurchased apps: $150K per year from Year 2 | Avalon planning assumption |
| Target run cost | Residual hosting, 1 retained app: $120K per year from Year 2 | Avalon planning assumption |
| Target run cost | Remaining licensing (managed DB, BYOL): $350K per year from Year 2 | Avalon planning assumption |
| Target run cost | Monitoring and cost-governance tooling: $80K per year from Year 2 | Avalon planning assumption |
| Agency program cost (Year 1) | Agency PMO, ISSO and UAT time: $300K | Avalon planning assumption |
| Agency program cost (Year 1) | Reassessment of the new boundary (assessor): $250K | Avalon planning assumption |
| Agency program cost (Year 1) | Legacy decommissioning and data sanitization: $100K | Avalon planning assumption |
| Agency program cost (Year 1) | Maintenance bridge on legacy hardware (no refresh): $150K | Avalon planning assumption |
| Labor rate | $165K fully loaded per sustainment FTE per year | Avalon planning assumption |
| Dual running | 75% of legacy run cost and 50% of cloud and SaaS run cost incurred in Year 1 | Waves cut over through the year |
| Avalon services | Per-application rates inside the market bands in Section 6 | Rehost $40K, replatform $95K, refactor $250K (T&M ceiling) |
| Discount rate | 1.3% real, mid-year convention | OMB Circular A-94 Appendix C, 5-year real rate for 2026 |
| Excluded | Cloud provider credits (shown only as a sensitivity), inflation, facility exit costs | Kept out to avoid overstating the case |