# The CMMC Pause Left DFARS 7012 in Place. Primes Still Own the Flowdown

> DoW suspended CMMC Phase 2 and its third-party assessments on July 13, 2026, but kept DFARS 252.204-7012 in effect. The clause and its companion, 252.204-7020, still put flowdown, incident reporting, and supplier self-assessment checks on the prime, and every one of those rests on a supplier's system security plan.

- Source: https://avalontechservices.com/news/the-cmmc-pause-left-dfars-7012-in-place-primes-still-own-the-flowdown
- Published: 2026-11-25
- Author: [Brandon Ireland](https://avalontechservices.com/author/brandon-ireland)
- Category: Authorization & Accreditation (A&A)
- Topic: Authorization & Accreditation (A&A)
- Publisher: Avalon Technology Services

## Key Takeaways

- A July 13, 2026 DoW CIO memo suspended the November 2026 move to CMMC Phase 2, halting third-party Level 2 and Level 3 assessment designations during review.
- The same memo kept DFARS 252.204-7012 in effect, so the flowdown, 72-hour incident reporting, and 90-day image preservation still apply to subcontractors.
- Under 252.204-7020, primes cannot award covered subcontracts unless the sub has a Basic NIST 800-171 assessment from the last three years.
- With third-party assessments paused, a supplier's self-score is what primes see, and that score is only as credible as the SSP behind it.
- Confirm which subs touch CDI, their SPRS scores, their current SSPs, their medium assurance certificates, and how cloud providers show FedRAMP Moderate equivalence.

On July 13, 2026, a [DoW CIO memorandum](https://dodcio.defense.gov/Portals/0/Documents/Library/ImplementingSuspensionCMMC-PhaseII.pdf), a non-GAO source, suspended the planned November 2026 move to CMMC Phase 2. Program managers can't designate third-party Level 2 or Level 3 assessments while the review runs. Four months earlier, in [GAO-26-107955](https://www.gao.gov/products/gao-26-107955), GAO had found that DoD had not assessed how it would handle the risk that private-sector assessor capacity would fall short.

The same memo says the cybersecurity requirements in DFARS 252.204-7012 remain in effect. For a prime with DoW programs that touch controlled unclassified information, the pause changed who checks a supplier's security, at least for now. The flowdown didn't change.

## What the Memo Stopped, and What It Left

| Suspended during the review | Still in effect |
| --- | --- |
| The November 2026 transition to Phase 2 | DFARS 252.204-7012 cybersecurity requirements |
| Designating CMMC Level 2 third-party (C3PAO) assessments | CMMC Level 1 and Level 2 self-assessments |
| Designating CMMC Level 3 (DIBCAC) assessments |  |
| Waivers |  |

The memo says further guidance will follow the CIO's 60-day review. GAO's recommendation, to assess and document the external factors that could affect the program, is open; DoD's corrective action plan targets December 31, 2026. Our Technical Brief on [CMMC assessment capacity and the Phase 2 pause](https://avalontechservices.com/technical-briefs/cmmc-assessment-capacity-what-gao-flagged-before-the-phase-2-pause) covers that finding and the sequence in detail.

## What Still Flows Down

Three obligations in the current clause text matter most for supplier management.

**Flowdown under 252.204-7012.** The [clause](https://www.acquisition.gov/dfars/252.204-7012-safeguarding-covered-defense-information-and-cyber-incident-reporting.) goes into subcontracts for operationally critical support or where performance will involve covered defense information. A subcontractor's covered systems are subject to NIST SP 800-171, and a cloud provider it uses must meet security requirements equivalent to the FedRAMP Moderate baseline.

**Incident reporting.** A contractor or subcontractor must report cyber incidents to DoD within 72 hours of discovery, using a DoD-approved medium assurance certificate, and preserve images of affected systems for at least 90 days. A subcontractor that reports must give the incident report number to the prime or the next higher tier as soon as practicable.

**A current self-assessment before award.** Under [252.204-7020](https://www.acquisition.gov/dfars/252.204-7020-nist-sp-800-171dod-assessment-requirements.), a prime may not award a subcontract subject to the 800-171 requirements unless the subcontractor has completed at least a Basic NIST SP 800-171 DoD Assessment within the last three years.

## A Self-Score Is Only as Good as the Plan Behind It

The clause defines a Basic Assessment as the contractor's own review of its system security plan, conducted under the DoD Assessment Methodology, with a confidence level of "Low" because the score is self-generated. With third-party Level 2 assessments suspended, that self-generated score is what a prime sees for most suppliers.

That [puts weight on the SSP](https://avalontechservices.com/capabilities/cybersecurity/authorization-and-accreditation/system-application-security-plans-ssp). A supplier whose plan is template language, or marks controls implemented when they are planned, produces a score that won't hold up when an assessor reads the plan. NIST SP 800-171 Rev. 2 requires the plan under 3.12.4, and CMMC carries the same requirement as practice CA.L2-3.12.4, so it is also the first document any future assessment model will need.

The same plans travel further than CMMC. In July 2026, GAO's [GAO-26-108606](https://www.gao.gov/products/gao-26-108606) counted five defense industrial base regulations among 117 cyber regulations it reviewed, including the CMMC rule and DFARS 252 with clause 7012. It also noted that IT contractors serving several agencies may have to report similar plans and assessments more than once. A supplier with one accurate plan answers each of those requests from the same source.

The capacity problem GAO flagged doesn't disappear during a pause. If third-party assessments resume, suppliers will compete for the same assessors, and the ones with accurate plans will be ready sooner.

## Supplier Checks Worth Doing Now

Capture and supply chain teams can do most of this without waiting for DoW's next guidance:

1. Confirm which subcontracts involve covered defense information, so the 7012 flowdown sits where it belongs.
2. Confirm each of those subcontractors has a Basic Assessment posted in SPRS within the last three years.
3. Ask whether the score reflects a current SSP for the system that will handle your program's data.
4. Confirm each subcontractor has a medium assurance certificate and knows to send you the DoD incident report number.
5. For suppliers using cloud services for covered information, ask how they show FedRAMP Moderate equivalence.

Proposals touch this too. Evaluators reading a DoW technical volume may look for how the offeror manages supplier cybersecurity, and "subcontractors will comply with DFARS 7012" is the answer every offeror gives.

## Where Avalon Fits

Avalon's [System & Application Security Plans white paper](https://avalontechservices.com/white-papers/system-application-security-plans-ssp) describes the plan work behind a credible self-score. Each implementation statement says who performs the control, what mechanism enforces it, how it works on this system, and where the evidence lives. Statuses stay accurate, so a planned control is routed to the gap log for the plan of action instead of being marked implemented, and inherited controls are checked against the provider's documentation. The paper notes that contractors handling CUI need their own SSP under 3.12.4, and that the craft is the same.

Avalon writes plans; it does not assess them, and it is not a CMMC third-party assessment organization.

If DoW program work that touches CUI is in your capture plan, Avalon teams as the sub that writes the system security plans your environment and your suppliers' self-assessments rest on.
